The third sprint of PI-12 is now complete. Key deliverables and progress are as follows:
- More than 70% of features targeted for this quarter are in development or complete
- We updated HarvardKey to better regulate who can claim and when
- We deployed an essential database update to support future XID work this quarter
- Operational work and requests to integrate applications with HarvardKey continues to grow sprint over sprint: 1198 tickets updated by IAM staff (an increase of 13% over last sprint) and completed 12 onboarding requests (+70%)
- Testing continues in partnership with HKS to prepare for IAM provisioning to their local Active Directory scheduled for 11/18