#  IAM PI-16 Mid-Point Update 

 





November 19, 2018

 

 

 Half of PI-16 (October 2018 - early January 2019) is complete and almost every planned feature has begun. So far we have released an update to improve user opt-in of Office365 and are very intensely focused on preparing for two major upgrades in early January of our Provisioning (IIQ) and Authentication systems. A quick summary of PI-16 progress is below.

###  PI-16 Progress

   ![pi-16 2](/sites/g/files/omnuum12676/files/styles/hwp_1_1__720x720_scale/public/iam/files/screen_shot_2018-11-19_at_9.56.37_am.png?itok=hsRVV-4W) 

 

Sort    Planned features 

  11 

  % of total 

    In Progress 

  8 

  73% 

    To Do 

  1 

  9% 

    Complete/Deferred 

  2 

  18% 

 



- Complete Features 
    - Add password sync to O365 email opt-in processes - Simplify O365 opt-in process by including password sync
- Deferred Features 
    - HarvardKey and email Qlik troubleshooting report for Support services - Determined that Qlik reporting of Provisioning data will require significant development in a future PI

###  Operational Statistics

   ![16-2-Ops](/sites/g/files/omnuum12676/files/styles/hwp_1_1__720x720_scale/public/iam/files/screen_shot_2018-11-19_at_10.03.06_am.png?itok=C_tGBC8I) 

 

 See the attached documents for full details about this PI and IAM project/operational statistics. You can learn more about how we do PI Planning and how to interpret the attached Summary/Priority reports by viewing our "[IAM Planning &amp; Progress Reporting](/news/iam-planning-progress-reporting)" overview post.



 

 

 

---

 Attachments- [  picture\_as\_pdf  iam\_pi\_16\_-\_sprint\_3\_summary\_report.pdf ](/sites/g/files/omnuum12676/files/iam_pi_16_-_sprint_3_summary_report.pdf)
- [  picture\_as\_pdf  iam\_pi-16\_-\_sprint\_3\_priorities.pdf ](/sites/g/files/omnuum12676/files/iam_pi-16_-_sprint_3_priorities.pdf)
 
---

 



 

 